New Year Sale

Why Buy PRINCE2 Practitioner Exam Dumps From Passin1Day?

Having thousands of PRINCE2 Practitioner customers with 99% passing rate, passin1day has a big success story. We are providing fully PRINCE2 exam passing assurance to our customers. You can purchase PRINCE2 Practitioner Exam exam dumps with full confidence and pass exam.

PRINCE2 Practitioner Practice Questions

Question # 1

A central government department, the Ministry of Food Hygiene (MFH), faces increasing pressure
to cut costs, better manage suppliers’ performance and reduce the confusion caused by
inadequate internal controls, outdated standards and outdated technology. External consultants
were employed to conduct a feasibility study to identify options to address the problems, and the
likely costs and benefits. The following options were considered:
Do nothing.
Re-engineer selected business functions.
Outsource selected business functions.
The feasibility study concluded that there was a case for outsourcing the MFH Information
Technology
Division and the Facilities Division (maintenance of buildings and grounds). The recommendations
were:
One service provider should be contracted to provide the services currently provided by the
Information Technology Division and the Facilities Division.
A 10-year service contract should be agreed with the selected service provider.
The feasibility study developed high-level designs of the current organization, processes, systems
and
operating models, plus an outline Business Case for the required project. The external consultants
also made the following recommendations for the management of the project:
Use PRINCE2.
Set up the project with 4 management stages:
Stage 1. Standard PRINCE2 initiation activities.
Stage 2. Create detailed designs (future organization, processes, systems and operating
models) and the service level agreement between MFH and the future service
provider.
Stage 3. Request and evaluate proposals, select service provider and agree contract.
Stage 4. Transfer equipment and staff, transfer responsibility for service provision and run
trial period.
Initial estimates indicated that the project would cost £2.5m and take two years to complete.
MFH senior management agreed that there was a case for outsourcing, and accepted the
recommendations as a basis for the project. There is an expected saving of £20m over 10 years.
The Outsourcing project has completed the Starting up a Project process and is now in the
initiation stage. Because of the strategic importance of the project, the MFH Chief Executive
Officer has taken the role of Executive. A PRINCE2-experienced Project Manager has been
appointed from within MFH. Staff within the business functions being outsourced will work with the
external consultants who conducted the feasibility study to define the detailed designs.
Which 2 statements should be recorded under the Timescale heading?

A.

The contract with the selected service provider will be agreed during stage 3.

B.

The expected benefits will be calculated over 10 years from completion of the project.

C.

If more MFH divisions are added to the scope of the services to be outsourced, the project
timescale will be extended and the realization of benefits will be delayed.

D.

The expected benefits should start to be realized as soon as the outsourced services become
operational at the end of stage 4.

E.

The transfer of equipment and staff is estimated to take six weeks.



A.

The contract with the selected service provider will be agreed during stage 3.


B.

The expected benefits will be calculated over 10 years from completion of the project.




Question # 2

While preparing the Quality Management Strategy, the Project Manager noticed that the corporate
quality management system does not specifically cover project management.
Which option provides an appropriate way for the Project Manager proceed?

A.

Record the development of a corporate quality management system for project management as
a prerequisite of the Project Plan.

B.

Proceed with the project without a Quality Management Strategy and adopt the selected
service provider's standards in stage 4.

C.


Seek relevant organizational standards, then facilitate a workshop to discuss the Quality
Management Strategy with Project Assurance



C.


Seek relevant organizational standards, then facilitate a workshop to discuss the Quality
Management Strategy with Project Assurance




Question # 3

Which of the following statements is NOT correct?
The Learn from Experience principle suggests that lessons should be actively sought...

A.

When Starting a Project

B.

When Initiating a Project

C.

 As the project progresses

D.

 As the project closes



B.

When Initiating a Project




Question # 4

Additional Information
Product Description

Quality notes from the Daily Log
The Director of Information Technology Division (DIT) has been asked to ensure that any changes
to the outsourced staff employment contracts adhere to employment law. The DIT will review
future job descriptions of the transferred staff before the final contract is signed with the selected
service provider.
The service level agreement between MFH and the selected service provider will specify the type
and quality of service required. The selected service provider must follow the industry standards
for providing outsourced services.
MFH has a quality management system which contains a document control procedure for all its
documentation, however this does not include change management.
All project documents will be subject to a quality review. Nominated products will require a formal
approval record signed-off by the quality review chair.
Extract from the draft Quality Management Strategy (may contain errors)
Introduction
1. This document defines the approach to be taken to achieve the required quality levels during
the project.
2. The Project Board will have overall responsibility for the Quality Management Strategy.
3. Project Assurance will provide assurance on the implementation of the Quality Management
Strategy.
Quality management procedure - Quality standards
4. The selected service provider will operate to industry standards for providing outsourced
services.
5. MFH document standards will be used.
Records
6. A Quality Register will be maintained to record the planned quality events and the actual results
from the quality activities.
7. Configuration Item Records will be maintained for each product to describe its status, version
and variant.
8. Approval records for products that require them will be stored in the quality database.
Roles and responsibilities
81
9. The DIT will check that the employment contracts for outsourced staff adhere to employment
law.
10. Team Managers will provide details of quality checks that have been carried out.
11. Team Managers will ensure that the Quality Register is updated with the names of team
members who are involved in the review process.
12. The Senior User will review the Product Descriptions of the products to be produced by the
selected service provider to ensure that they can be achieved.
The service level agreement looks like any other MFH document.

A.

Obtain agreement from the Director of Facilities Division to redesign the service level
agreement within the remaining +2 days tolerance.

B.

Raise an issue (off-specification).

C.

Accept this error as a concession.

D.

 No action required



D.

 No action required




Question # 5

Which principle is supported by the activity Evaluate the Project?

A.

Continued Business Justification

B.

Defined roles and responsibilities

C.

Learn from experience

D.

Manage by stages



C.

Learn from experience




Question # 6

Scenario:
Techniques, processes and procedures
1. Any threat that may result in a loss of MFH data must be escalated immediately.
Joint agreements
2. Work is to start at the beginning of week 2 (Stage 4).
3. The project will take two years to complete, at an estimated cost of £2.5m.
Tolerances
4. None.
Constraints
5. MFH staff must not be involved in any heavy lifting during the removal of existing IT equipment.
6. Installation work must take place during MFH normal working hours.
7. +£10,000 / -£25,000.
Reporting arrangements
8. Highlight Report every Monday by 10.00 am.
9. The report must contain a summary of all products worked on during the previous week.
10. Project Manager must be notified of any issues immediately by telephone.
Problem handling and escalation
11. Impact analysis of all issues must be completed within 24 hours.
Extracts or references
12. The Stage Plan for stage 4 is available from Project Support.
Approval method
13. Project Assurance will review the completed Work Package and confirm completion
Column 1 is a list of actions that occur during the Controlling a Stage process. For each action in
Column 1, select from Column 2 the PRINCE2 theme that is being applied. Each selection from
Column 2 can be used once, more than once or not at all.
Drop down the answer from column 1 to column 2.



Question # 7

Which project controls should be established for the Outsourcing project?

A.

Highlight Reports to the Project Manager; Exception Reports to the Project Board when project
tolerances are forecast to be exceeded.

B.

Highlight Reports to the Project Board; Exception Reports to corporate management when
stage tolerances are forecast to be exceeded.

C.

 Highlight Reports to the Project Board; Exception Reports to the Project Board when stage or
project tolerances are forecast to be exceeded.



C.

 Highlight Reports to the Project Board; Exception Reports to the Project Board when stage or
project tolerances are forecast to be exceeded.




Question # 8

The Work Package has been in progress for four weeks and has four weeks remaining. The
Information Technology Team Manager is concerned that he has no idea what the service
provider is doing about preparing to accept the transfer of Information Technology equipment and
staff. He is uncertain about what should be happening.
Which 2 initial actions should the Team Manager take in response to this concern?

A.

Notify the Project Manager by raising an Exception Report.

B.

Raise this concern in the next fortnightly Checkpoint Report.

C.

Check the Communication Management Strategy to ascertain what records of communications
with the service provider are required.

D.

Check the Information Technology Work Package for development interfaces to see whether
the service provider Team Manager should have been liaising with the Information Technology
team during development.

E.

Raise an issue to notify the Project Manager of this concern.



D.

Check the Information Technology Work Package for development interfaces to see whether
the service provider Team Manager should have been liaising with the Information Technology
team during development.


E.

Raise an issue to notify the Project Manager of this concern.




PRINCE2 Practitioner Dumps
  • Up-to-Date PRINCE2 Practitioner Exam Dumps
  • Valid Questions Answers
  • PRINCE2 Practitioner Exam PDF & Online Test Engine Format
  • 3 Months Free Updates
  • Dedicated Customer Support
  • PRINCE2 Certification Pass in 1 Day For Sure
  • SSL Secure Protected Site
  • Exam Passing Assurance
  • 98% PRINCE2 Practitioner Exam Success Rate
  • Valid for All Countries

PRINCE2 PRINCE2 Practitioner Exam Dumps

Exam Name: PRINCE2 Practitioner Exam
Certification Name: PRINCE2 Certification

PRINCE2 PRINCE2 Practitioner exam dumps are created by industry top professionals and after that its also verified by expert team. We are providing you updated PRINCE2 Practitioner Exam exam questions answers. We keep updating our PRINCE2 Certification practice test according to real exam. So prepare from our latest questions answers and pass your exam.

  • Total Questions: 190
  • Last Updation Date: 17-Feb-2025

Up-to-Date

We always provide up-to-date PRINCE2 Practitioner exam dumps to our clients. Keep checking website for updates and download.

Excellence

Quality and excellence of our PRINCE2 Practitioner Exam practice questions are above customers expectations. Contact live chat to know more.

Success

Your SUCCESS is assured with the PRINCE2 Practitioner exam questions of passin1day.com. Just Buy, Prepare and PASS!

Quality

All our braindumps are verified with their correct answers. Download PRINCE2 Certification Practice tests in a printable PDF format.

Basic

$80

Any 3 Exams of Your Choice

3 Exams PDF + Online Test Engine

Buy Now
Premium

$100

Any 4 Exams of Your Choice

4 Exams PDF + Online Test Engine

Buy Now
Gold

$125

Any 5 Exams of Your Choice

5 Exams PDF + Online Test Engine

Buy Now

Passin1Day has a big success story in last 12 years with a long list of satisfied customers.

We are UK based company, selling PRINCE2 Practitioner practice test questions answers. We have a team of 34 people in Research, Writing, QA, Sales, Support and Marketing departments and helping people get success in their life.

We dont have a single unsatisfied PRINCE2 customer in this time. Our customers are our asset and precious to us more than their money.

PRINCE2 Practitioner Dumps

We have recently updated PRINCE2 PRINCE2 Practitioner dumps study guide. You can use our PRINCE2 Certification braindumps and pass your exam in just 24 hours. Our PRINCE2 Practitioner Exam real exam contains latest questions. We are providing PRINCE2 PRINCE2 Practitioner dumps with updates for 3 months. You can purchase in advance and start studying. Whenever PRINCE2 update PRINCE2 Practitioner Exam exam, we also update our file with new questions. Passin1day is here to provide real PRINCE2 Practitioner exam questions to people who find it difficult to pass exam

PRINCE2 Certification can advance your marketability and prove to be a key to differentiating you from those who have no certification and Passin1day is there to help you pass exam with PRINCE2 Practitioner dumps. PRINCE2 Certifications demonstrate your competence and make your discerning employers recognize that PRINCE2 Practitioner Exam certified employees are more valuable to their organizations and customers.


We have helped thousands of customers so far in achieving their goals. Our excellent comprehensive PRINCE2 exam dumps will enable you to pass your certification PRINCE2 Certification exam in just a single try. Passin1day is offering PRINCE2 Practitioner braindumps which are accurate and of high-quality verified by the IT professionals.

Candidates can instantly download PRINCE2 Certification dumps and access them at any device after purchase. Online PRINCE2 Practitioner Exam practice tests are planned and designed to prepare you completely for the real PRINCE2 exam condition. Free PRINCE2 Practitioner dumps demos can be available on customer’s demand to check before placing an order.


What Our Customers Say