Question # 1 Extract from the Project Product Description (with errors) Which 2 statements apply to the Customer's quality expectations section?
A. Delete entry 16 because this should be shown on the Product Description for the photos.
B. Delete entry 17 because this is beyond the scope of this project.
C. Delete entry 18 because standards should NOT be shown here.
D. Delete entry 19 because this should appear in the Product Description for the calendar and not the Project Product Description.
E. Delete entry 20 because this is an expected benefit and should be recorded in the Business Case
Click for Answer
B. Delete entry 17 because this is beyond the scope of this project.
E. Delete entry 20 because this is an expected benefit and should be recorded in the Business Case
Question # 2 Project Scenario Calendar Project (Note: The companies and people within the scenario are fictional.) There has been a reduction in fie number of orders at the MNO Manufacturing Company due in part to the increased marketing activities of its competitors. To help counter this, the company has decided to create a promotional calendar for next year for all its current and prospective customers. The end product of this project will be a prepared calendar pack, ready for printing. The design of the calendar will be similar to one sent out previously, and must reflect the company image as described in the existing corporate branding standards. Another project is currently producing a new company logo when is to be printed on each page of the promotional calendar. The prepared calendar pack will consist of: Design for each month - correctly showing at public holidays and new company logo Selected photographs- 12 professionally-produced photographs, showing different members of staff Selected paper and selected envelope - for printing and mailing the calendar Chosen label design - a competition to design a label will be held as part of this project List of customers - names and addresses of customers to whom the calendar will be sent. The project is currently in initiation and will have two further stages: Stage 2 will include tie activities to: Create the customer fast using information from the Accounts and Marketing departments Confirm compliance with the Data Protection Legislation Create a design for each month - this will be done by the internal creative team Select and appoint a professional photographer Gather photograph design ideas from previous project and agree photographic session schedule Prepare a production cost forecast Select paper and envelope. Stage 3 will include the activities to: Produce and select tie professionally-taken photographs Hold the label design competition and choose the label design Assemble the prepared calendar pack. A production cost forecast, based on the options and costs for the paper, envelope, printing and marketing of the calendar is to be produced in stage 2. However, the actual production and distribution of the calendars is not within the scope of the project. The product cost forecast will be reviewed by the Project Board to determine whether tie project should continue. It is now 05 October and the prepared calendar pack must be delivered to the print company by 30 November, to enable printing and distribution of the calendar in time for Christmas. The cost of the activities to develop the specialist products and the cost of the project management activities are estimated to be £20,000. There is a project time tolerance of +1 week /-2 weeks and a project cost tolerance of +£6,000 / -£6,000. A change budget of £500 has been allocated but there is no risk budget. As the project approaches the end of stage 2, the Project Manager has requested a Product Status Account to ensure that all products are at their expected point of development. Although the list of customers has been quality reviewed, it has not been baselined because the Marketing department have not provided all of the prospective customers' details. What initial action should the Project Manager take?
A. Delay producing the End Stage Report until the list of customers has been baselined.
B. Raise an Exception Report to the Project Board to highlight the issue.
C. Check the target sign-off date for the list of customers.
D. Update the product status to baselined and obtain a commitment from the Marketing department to finish this work within the next few days.
Click for Answer
C. Check the target sign-off date for the list of customers.
Question # 3 Who is responsible for ensuring that Communication Management Strategy is appropriate and that planned communication activities actually take place?
A. Project Assurance
B. Project Manager
C. Corporate or Programme Management
D. Project Support
Click for Answer
Question # 4 If Project tolerances were threatened, who needs to be notified?
A. Project Board
B. Project Manager
C. Corporate or Programme Management
D. Executive
Click for Answer
C. Corporate or Programme Management
Question # 5 Scenario A central government department, the Ministry of Food Hygiene (MFH), faces increasing pressure to cut costs, better manage suppliers’ performance and reduce the confusion caused by inadequate internal controls, outdated standards and outdated technology. External consultants were employed to conduct a feasibility study to identify options to address the problems, and the likely costs and benefits. The following options were considered: Do nothing. Re-engineer selected business functions. Outsource selected business functions. The feasibility study concluded that there was a case for outsourcing the MFH Information Technology Division and the Facilities Division (maintenance of buildings and grounds). The recommendations were: One service provider should be contracted to provide the services currently provided by the Information Technology Division and the Facilities Division. A 10-year service contract should be agreed with the selected service provider. The feasibility study developed high-level designs of the current organization, processes, systems and operating models, plus an outline Business Case for the required project. The external consultants also made the following recommendations for the management of the project: Use PRINCE2. Set up the project with 4 management stages: Stage 1. Standard PRINCE2 initiation activities. Stage 2. Create detailed designs (future organization, processes, systems and operating models) and the service level agreement between MFH and the future service provider. Stage 3. Request and evaluate proposals, select service provider and agree contract. Stage 4. Transfer equipment and staff, transfer responsibility for service provision and run trial period. Initial estimates indicated that the project would cost £2.5m and take two years to complete. MFH senior management agreed that there was a case for outsourcing, and accepted the recommendations as a basis for the project. There is an expected saving of £20m over 10 years. The Outsourcing project has completed the Starting up a Project process and is now in the initiation stage. Because of the strategic importance of the project, the MFH Chief Executive Officer has taken the role of Executive. A PRINCE2-experienced Project Manager has been appointed from within MFH. Staff within the business functions being outsourced will work external consultants who conducted the feasibility study to define the detailed designs. Which 2 statements should be recorded under the Business options heading?
A. The re-engineering of selected business functions would not provide the required outcome.
B. The lack of up-to-date technology in MFH means a re-engineering of existing services will not necessarily deliver the performance improvements required.
C. Use external consultants to provide guidance on the detailed design of the outsourced services.
D. Set up a PRINCE2 project to deliver the outsourced services.
E. Review a list of service providers to determine a short-list of possible service providers
Click for Answer
C. Use external consultants to provide guidance on the detailed design of the outsourced services.
D. Set up a PRINCE2 project to deliver the outsourced services.
Answer Description http://www.whatisprince2.net/prince2-theme-business-case.php
Question # 6 Extract from the Project Product Description (with errors) Which 2 statements apply to the Acceptance criteria section?
A. Amend entry 21 to 'Appearance - 12 photos each showing different members of staff.
B. Move entry 21 to Composition because the photos are part of the final product.
C. Delete entry 22 because the development of the new company logo is not within the scope of the Calendar project.
D. Move entry 23 to Derivation because the Data Protection Act already exists.
E. Delete entry 24 because this is NOT a suitable acceptance criteria for this project
Click for Answer
A. Amend entry 21 to 'Appearance - 12 photos each showing different members of staff.
C. Delete entry 22 because the development of the new company logo is not within the scope of the Calendar project.
Question # 7 Additional Information Extract from the Communication Management Strategy. The project information in the table below is true, but it may not be recorded under the correct heading or be in the correct document. Using the Project Scenario, select the appropriate response to each of the following 5 questions which have been raised by the Project Board. The project is now at the end of the initiation stage. Having decided that the Calendar project is a relatively simple project, the Project Manager combined the Starting Up a Project process and the Initiating a Project process. No Project Brief has been produced. Instead the Project Manager used the project mandate to produce a simple Project Initiation Documentation (PlO). The PlO includes the Business Case, a product checklist and several Product Descriptions, Including the Project Product Description. Short sections are also included for each of the strategies and the controls to be applied. The Project Manager has elected to use the Daily Log to record all risks, issues. lessons and quality - results. After the initiation stage there will be two further stages during which a small number of Work Packages will be authorized. While these are being managed, the Project Manager will hold regular checkpoints, which will support the production of weekly Highlight Reports to the Project Board. There is no Project Brief. How can there be a common understanding of the desired outcomes for the prepared calendar pack?
A. The simple Project Initiation Documentation contains the Quality Management Strategy. This contains details of the acceptance criteria for this project.
B. The Project Brief should have been produced and approved before the project progressed into the initiation stage.
C. The simple Project Initiation Documentation contains the project definition.
Click for Answer
C. The simple Project Initiation Documentation contains the project definition.
Question # 8 Scenario: Techniques, processes and procedures 1. Any threat that may result in a loss of MFH data must be escalated immediately. Joint agreements 2. Work is to start at the beginning of week 2 (Stage 4). 3. The project will take two years to complete, at an estimated cost of £2.5m. Tolerances 4. None. Constraints 5. MFH staff must not be involved in any heavy lifting during the removal of existing IT equipment. 6. Installation work must take place during MFH normal working hours. 7. +£10,000 / -£25,000. Reporting arrangements
8. Highlight Report every Monday by 10.00 am. 9. The report must contain a summary of all products worked on during the previous week. 10. Project Manager must be notified of any issues immediately by telephone. Problem handling and escalation 11. Impact analysis of all issues must be completed within 24 hours. Extracts or references 12. The Stage Plan for stage 4 is available from Project Support. Approval method 13. Project Assurance will review the completed Work Package and confirm completion Which 2 statements apply to either the Extracts or references or Approval method sections?
A. Delete entry 12 because this should be the Team Plan not the Stage Plan.
B. A suitable entry for Extracts or references would be 'Product Descriptions are available from Project Support'.
C. Move entry 13 to Reporting arrangements because this describes how completion will be advised to the
D. Project Manager.
E. Delete entry 13 because this is NOT a Project Assurance responsibility.
Click for Answer
A. Delete entry 12 because this should be the Team Plan not the Stage Plan.
B. A suitable entry for Extracts or references would be 'Product Descriptions are available from Project Support'.
Up-to-Date
We always provide up-to-date PRINCE2 Practitioner exam dumps to our clients. Keep checking website for updates and download.
Excellence
Quality and excellence of our PRINCE2 Practitioner Exam practice questions are above customers expectations. Contact live chat to know more.
Success
Your SUCCESS is assured with the PRINCE2 Practitioner exam questions of passin1day.com. Just Buy, Prepare and PASS!
Quality
All our braindumps are verified with their correct answers. Download PRINCE2 Certification Practice tests in a printable PDF format.
Basic
$80
Any 3 Exams of Your Choice
3 Exams PDF + Online Test Engine
Buy Now
Premium
$100
Any 4 Exams of Your Choice
4 Exams PDF + Online Test Engine
Buy Now
Gold
$125
Any 5 Exams of Your Choice
5 Exams PDF + Online Test Engine
Buy Now
Passin1Day has a big success story in last 12 years with a long list of satisfied customers.
We are UK based company, selling PRINCE2 Practitioner practice test questions answers. We have a team of 34 people in Research, Writing, QA, Sales, Support and Marketing departments and helping people get success in their life.
We dont have a single unsatisfied PRINCE2 customer in this time. Our customers are our asset and precious to us more than their money.
PRINCE2 Practitioner Dumps
We have recently updated PRINCE2 PRINCE2 Practitioner dumps study guide. You can use our PRINCE2 Certification braindumps and pass your exam in just 24 hours. Our PRINCE2 Practitioner Exam real exam contains latest questions. We are providing PRINCE2 PRINCE2 Practitioner dumps with updates for 3 months. You can purchase in advance and start studying. Whenever PRINCE2 update PRINCE2 Practitioner Exam exam, we also update our file with new questions. Passin1day is here to provide real PRINCE2 Practitioner exam questions to people who find it difficult to pass exam
PRINCE2 Certification can advance your marketability and prove to be a key to differentiating you from those who have no certification and Passin1day is there to help you pass exam with PRINCE2 Practitioner dumps. PRINCE2 Certifications demonstrate your competence and make your discerning employers recognize that PRINCE2 Practitioner Exam certified employees are more valuable to their organizations and customers. We have helped thousands of customers so far in achieving their goals. Our excellent comprehensive PRINCE2 exam dumps will enable you to pass your certification PRINCE2 Certification exam in just a single try. Passin1day is offering PRINCE2 Practitioner braindumps which are accurate and of high-quality verified by the IT professionals. Candidates can instantly download PRINCE2 Certification dumps and access them at any device after purchase. Online PRINCE2 Practitioner Exam practice tests are planned and designed to prepare you completely for the real PRINCE2 exam condition. Free PRINCE2 Practitioner dumps demos can be available on customer’s demand to check before placing an order.
What Our Customers Say
Jeff Brown
Thanks you so much passin1day.com team for all the help that you have provided me in my PRINCE2 exam. I will use your dumps for next certification as well.
Mareena Frederick
You guys are awesome. Even 1 day is too much. I prepared my exam in just 3 hours with your PRINCE2 Practitioner exam dumps and passed it in first attempt :)
Ralph Donald
I am the fully satisfied customer of passin1day.com. I have passed my exam using your PRINCE2 Practitioner Exam braindumps in first attempt. You guys are the secret behind my success ;)
Lilly Solomon
I was so depressed when I get failed in my Cisco exam but thanks GOD you guys exist and helped me in passing my exams. I am nothing without you.